What's the difference of Manually control project execution and Automatically execute activities and deliver tasks in ProjectLink
Modified: 30-May-2024
Applies To
- Windchill ProjectLink 10.0 to 13.0
Description
- What's the difference of Manually control project execution and Automatically execute activities and deliver tasks of Execution Control
- What's the features of Manually control project execution
- What's the features of Automatically execute activities and deliver tasks
- In projects with manually control project execution mode, the owner of an activity can still edit its attributes after the activity is complete
- Can track working hours of activities after project start, even if activities have not been completed when project is manually control project execution mode